COUNTY'S DEBRIS REMOVAL EFFORT PASSES THE 400,000 CUBIC
YDS. MARK
FORT MYERS, Fla. (September 11, 2004) - Lee County has collected more than
435,000 cubic yards of horticultural debris since the Hurricane Charley
post-disaster recovery began.
As of Sep. 8 (last Wednesday), Lee County had collected 435,980 cubic yards
of horticultural and construction & demolition debris (load tickets run several
days behind because of time needed to input them into an accounting system).
The county is continuing the mass effort, however, due to Hurricane Ivan,
activities may be curtailed Monday (Sep. 13).
For a status of what neighborhoods the county is working in, or plans to
pickup, visit www.lee-county.com and click
on "Debris Removal Information."
Here's Friday's status:
SFM Area - Started 8/19/04
- Plantation Rd area S of McG Bap Chrch done, Entrada, Casamada, E of
Southpoint done.
- Pine Manor, Page Park, Beacon Manor, Briarcliff, Island Pk,
Brentwood, Pinecrest Reflection Lakes
complete.
- Overlook area, Fiesta Village, Southpoint, Tanglewood, Macgregor,
Villas area complete
- Kelley Green, Cook Rd, Kelley Rd area 98%. Working Pine Ridge,
Kelley Rd, AW Bulb area all 98%
- The Forest, Harborage, and Paradise Park complete. Gateway 95%,
Fiddlesticks, Eagle Rdge complete
- Working Heritage Farms (held up by Francis flooding) and Harlem
Heights areas, heavy rebound all 95%
- Working Eldorado Estates, Fountain Lakes, Strike Lane area, shld be
compl today
Pine Island - Started 8/20/04
- Working St. James, Island Marina. Stringfellow Rd hort complete. C&D
done, W side Stringfellow N of
Center to Alcorn
- C&D done in Alden Pines, Working areas E and W of Oleander Dr.
- Hort 50% in Alden Pines, Hort, Center to Alcorn W side complete
- Picking up C&D in St James York St areas. Grinding hort. Start night
hauling of C&D to landfill tonight
NFM Area - Started 8/26/04
- Moody Rd area compl. Palmona Pk, Piney Area Wway Ests, Old Bridge,
complete
- Working Suncoast (heavy area) 80% compl. Working Slater to
Williamsburg Rd 60%
- Working area N of Bayshore, Yacht Club Colony, River Bend areas
- Working N side of Pondella, Grinding Hort.
Captiva - Started 8/26/04 Minimal work on 9/6/04
- N of Andy R Ln compl. Completed W side and E side of Captiva Dr.
Working 2nd pass.
- Start direct haul of C&D today
- Hazard trees are being felled, cut, and hauled to staging, 80 done
85 to go. Working 2nd pass in Village
East FM - Started 8/30/04
- Working Alabama Groves 85%, Morse Shores done, Working Tice area at
Glenwood Ave
- Olga to FM Shores (Warner Rd) 90%. Started Orange River Rd and
Cemetary Rd working W to E