Before Project After Project
Updated 1-15-07
Project Description
Matanzas Pass has been dredged 8 times previously, dating back to 1961. The latest dredging activity took place in Spring of 2001. Approximately 180,000 cyds of material were removed from the navigation channel and placed on Ft. Myers Beach.
The U.S. Army Corps of Engineers (USACE) has historically maintained the channel, however, the County conducted a maintenance activity in 1996. USACE is planning another maintenance event; however, it is expected construction will begin no earlier than Fall 2010. Cost estimates for the project have not been provided.
©2005 Lee County Official Website
County Government Information: (239) 332-2737 www.lee-county.com
For Questions or Comments, please contact Robert Neal at Rneal@leegov.com
|