Halfway Creek Restoration

Project Objective: Initial phase will include drainage and water quality improvements for Halfway Creek by removing the FPL berm within the limits shown above. The banks around the restored opening will become a littoral shelf, and planted with native vegetation.
Expected Completion Date: 2009
Available budget: $800,000
Project Status: In Permitting.
Monthly Progress Meeting Summary:
Contact information:
Steven Farah, Project Mgr.
Phone: 239-533-8829;
E-mail: Farahsa@leegov.com