|
Proj. No. |
Projects |
Description |
Manager |
|
6002 |
12th
Street W. Sidewalk Gunnery to Sunshine Blvd. |
04/15/08
no change funds
available, bid documents being prepared. |
Sarah
Clarke |
|
4083 |
A & W Bulb Improvements |
|
Mike
Rigsby
Rob Phelan |
|
5034 |
Alico Rd. Connector
Alignment Study. |
04/15/08 Alignment agreed upon with
Jamersons Farms. Centerline survey complete.
Information to county lands for appraisal to
determine if a voluntary purchase of the
right-of-way needed through the Jamerson
parcel can be negotiated. |
Sarah
Clarke
|
|
4030 |
Alico Rd. Ditch ROW |
04/15/08 - processing resolution of necessity
for specific properties. |
Don
DeBerry |
|
4030 |
Alico Road 6-Laning |
|
Don
DeBerry |
|
4030 |
Alico Rd. / Pennsylvania
St. Connector & Signal |
04/15/08 - 100% plans complete; ROW obtained.
CM contract to Board for approval 4/22 . |
Don
DeBerry |
|
6002 |
Arthur Sidewalk |
|
Randy Cerchie |
|
6047 |
Boca Grande Drainage. |
04/15/08 - Project Completed. |
Eyra Cash |
|
4044 |
Bonita Beach Road US 41
to Old US 41 Phase III. |
04/15/08 no change, 30% roadway plans
schedule for submittal September 2008 |
Eyra Cash |
|
6002 |
Bonita Beach Road Sidewalk |
|
Eyra Cash |
|
6002 |
Bonita Beach Road Sidewalk
from Bonita Grande to I-75 |
|
Eyra Cash |
|
4044 |
Bonita Beach RoadPhase II. |
04/15/08 no change, SFWMD permit submitted.
Construction and Right-of-Way Plans to be
finalized. Right-of-Way acquisition is
schedule to be completed by July 08. |
Eyra Cash |
|
0700 |
Brantley Rd. US 41 to
Summerlin canal barrier system. |
04/15/08 Final plans and engineers
estimate being prepared. Will let for bids
summer 08. |
Sarah
Clarke |
|
4030 |
Briarcliff Canal Filter
Marsh. |
04/15/08 - Agency Approval received.
Coordinating contracts, applying for gopher
tortoise relocation permit. |
Betsie
Hiatt |
|
6002 |
Buckingham Rd. Paved
Shoulders. |
04/15/08 Project on hold. |
Sarah
Clarke |
|
4088 |
Burnt
Store Widening. |
04/15/08 no change,
Received 30% plans. |
Mike
Rigsby |
|
4020 |
Business 41 from Marianna
to Littleton Rd. |
|
Don
DeBerry |
|
5033 |
Cape Coral Parkway / Del
Prado Turn Lane |
04/15/08 - Sent 90% Plans comments from LCDOT/CC
to Consultant. Evaluating cost of ITS and sign
components required for variable triple lefts
lane assignments, may run triple left 24-7
|
Rob Phelan |
|
5815 |
Cape Coral Toll |
|
Paul
Wingard |
|
4683 |
Captiva Drive CCCL Permit. |
04/15/08 Under construction. Dune
restoration will commence when construction
complete end of May. |
Betsie
Hiatt |
6713 |
Coconut Road Widening West
of US 41 |
|
Rob Phelan |
|
0700 |
College Parkway Drainage |
|
Sarah
Clarke |
|
4054 |
Colonial
Blvd. from I-75 to SR 82, 4 Lane to 6 Lane. |
04/15/08 no change, 60%
plans complete. |
Mike
Rigsby |
|
5054 |
Colonial Blvd. / McGregor
to I - 75. |
04/15/08 Comments received from FDOT on
traffic report and are being addressed.
Working toward recommending a preferred
alignment. |
Sarah
Clarke |
|
6064 |
Colonial Blvd. / Metro
Pkwy. Queue Jump. |
04/15/08 Comments on 30% plans being
addressed. Comments received form FDOT on the
pavement design and typical section. |
Sarah
Clarke |
|
|
Colonial initiative |
04/15/08 - Selected consultant, ranking
approved by BoCC 4/15/2008, will begin
negotiating contract |
Don
DeBerry |
|
4723 |
Corkscrew Mitigation |
|
Betsie
Hiatt |
|
0700 |
Corkscrew Road Curve. |
04/15/08
no change, Under construction |
Eyra Cash |
|
4078 |
CR 951 Extension. |
04/15/08 - no change, Draft EIS sent to Federal
Highway. Voluntary right of way
acquisition underway. |
Don
DeBerry |
|
4083 |
Cutlass Drive. |
04/15/08 no change, Preparing
preliminary plans for drainage improvements
and resurfacing of road, met with channel
drain manufacturer to discuss product, site
visit indicated that at some location the use
of the valley gutter may be feasible. |
Rob Phelan |
|
|
Daniels Fire Station |
04/15/08 - In permitting / 0.47 credits at
Island Park |
Betsie
Hiatt |
|
TBD |
Daniel Parkway 4 Lane
Widening. |
04/15/08 no change, Collecting available data on
project |
Rob Phelan |
|
6713 |
Daniels Pkwy. / Treeline
Av. Dual Left-Turn Lane. |
04/15/07 no
change, 100%
design plans complete. Received General
Permit. |
Eyra Cash |
|
6713 |
Daniels Pkwy & Bell Tower
Dr. |
04/15/08 no change, Will
be bid with the Daniels and Treeline Av.
project. Construction to start in 2008 |
Lora Celec |
|
6713 |
Del Prado / Cape Coral Pkwy
Turn Lane |
|
Rob Phelan |
|
6742 |
Del Prado Blvd. Median
Improvements. |
04/15/08 no change, Consultant working on
100% plans. |
Eyra Cash |
|
5066 |
Duke Highway |
|
Randy Cerchie |
|
5067 |
Estero Blvd Phase 1  |
03/19/08 - Held Public Meeting on March 19/08
Meet with FMB Chamber of Commerce
Meeting with BPAC April 16/08
Schedule 2 additional Public Meetings |
Rob Phelan |
|
|
Estero Parkway Extension
East of Ben Hill Griffin |
|
Rob Phelan |
|
5021 |
Estero Parkway from Three
Oaks to Ben Hill Griffin |
|
Nicole Maxey |
|
0700 |
Evans Connector Metro
Pkwy. to Evans Ave. |
04/15/08 no change Final report being prepared to
recommend an alignment. |
Sarah
Clarke |
|
4043 |
Gator Hole Preserve
Tortoise Relocation. |
04/15/08 Initial land management for Phase 2
(80 acres) complete. Initiating FWC relocation
site permit. Conduct Alico / Pennslvania
tortoise relocation in approximately 1 month. |
Betsie
Hiatt |
|
4083 |
Gladiolus Drive 4-Laning from Winkler to Pine
Ridge Road including A&W Bulb Road and Bass
Road Widening |
04/15/08 Contract approved at April 15, 2008
BOCC meeting. Updating A&W Plans based on Topo
Data received from Cooner survey.
|
Rob Phelan |
|
6002 |
Glenwood
Ave sidewalk (Ortiz to Prospect) & Tice St
(Ortiz to Lexington) |
04/15/08 no change, Under Construction. |
Eyra Cash |
4055 |
Gunnery Road  |
Under construction |
Nicole Maxey |
|
6002 |
Gunnery Sidewalk Lehigh
HS to Buckingham Rd. |
04/15/08 no change, under construction (NTP
issued 2/18/08). |
Sarah
Clarke |
|
5721 |
Hancock Bridge Extension |
|
Sarah
Clarke |
|
4083 |
Hidden Lakes Mitigation
Area. |
04/15/08 no change,
Exotic Maintenance and monitoring ongoing. |
Betsie
Hiatt |
|
6713 |
Homestead & Milwaukee Turn
Lane. |
04/15/08, (Westbound left turn lane on
Milwaukee Blvd.) 60% review comments are being
incorporated into the design. |
Lora Celec |
|
5063 |
Homestead
Rd. South of Sunrise to Alabama. |
04/15/08 drainage design being finalized,
SFWMD permit being prepared. 60% comments have
been addressed. Working toward 90% plans
submittal. |
Sarah
Clarke |
|
6713 |
Homestead Rd. & Beth Stacey
Blvd. |
03/18/08 -Construction of roadway and signal
completed. |
Lora Celec |
|
6002 |
Homestead Rd. Sidewalk. |
04/15/08 - no change, Project on hold. |
Sarah
Clarke |
|
4723 |
Imperial Marsh Preserve
Wetland and Panther Mitigation Area Corkscrew
Mitigation. |
04/15/08 no change Exotic
Maintenance and monitoring ongoing. |
Betsie
Hiatt |
|
4060 |
Imperial Street 4-Laning
from Bonita Beach Road to E. Terry Street  |
|