6002 12th Street W. – Sidewalk Gunnery to Sunshine Blvd. 04/15/08 –  no change – funds available, bid documents being prepared. Sarah Clarke
4083 A & W Bulb Improvements   Mike Rigsby Rob Phelan
5034 Alico Rd. Connector Alignment Study. 04/15/08 – Alignment agreed upon with Jamersons Farms. Centerline survey complete. Information to county lands for appraisal to determine if a voluntary purchase of the right-of-way needed through the Jamerson parcel can be negotiated.
Sarah Clarke
 
4030 Alico Rd. Ditch ROW— 04/15/08 - processing resolution of necessity for specific properties. Don DeBerry
4030 Alico Road 6-Laning   Don DeBerry
4030 Alico Rd. / Pennsylvania St. Connector & Signal 04/15/08 - 100% plans complete; ROW obtained. CM contract to Board for approval 4/22 . Don DeBerry
6002 Arthur Sidewalk   Randy Cerchie
6047 Boca Grande Drainage. 04/15/08 - Project Completed. Eyra Cash
4044 Bonita Beach Road – US 41 to Old US 41 Phase III. 04/15/08 –  no change, 30% roadway plans schedule for submittal September 2008  Eyra Cash
6002 Bonita Beach Road Sidewalk   Eyra Cash
6002 Bonita Beach Road Sidewalk from Bonita Grande to I-75   Eyra Cash
4044 Bonita Beach Road—Phase II. 04/15/08 – no change, SFWMD permit submitted. Construction and Right-of-Way Plans to be finalized. Right-of-Way acquisition is schedule to be completed by July 08. Eyra Cash
0700 Brantley Rd. – US 41 to Summerlin – canal barrier system. 04/15/08 –  Final plans and engineers estimate being prepared. Will let for bids summer ’08. Sarah Clarke
4030 Briarcliff Canal Filter Marsh. 04/15/08 - Agency Approval received. Coordinating contracts, applying for gopher tortoise relocation permit. Betsie Hiatt
6002 Buckingham Rd. Paved Shoulders. 04/15/08 – Project on hold. Sarah Clarke
4088 Burnt Store Widening. 04/15/08 – no change, Received 30% plans. Mike Rigsby
4020 Business 41 from Marianna to Littleton Rd.   Don DeBerry
5033 Cape Coral Parkway / Del Prado Turn Lane 04/15/08 - Sent 90% Plans comments from LCDOT/CC to Consultant. Evaluating cost of ITS and sign components required for variable triple lefts lane assignments, may run triple left 24-7
 
Rob Phelan
5815 Cape Coral Toll   Paul Wingard
4683 Captiva Drive CCCL Permit. 04/15/08 – Under construction. Dune restoration will commence when construction complete – end of May. Betsie Hiatt
6713 Coconut Road Widening West of US 41   Rob Phelan
0700 College Parkway Drainage   Sarah Clarke
4054 Colonial Blvd. from I-75 to SR 82, 4 Lane to 6 Lane. 04/15/08 – no change, 60% plans complete. Mike Rigsby
5054 Colonial Blvd. / McGregor to I - 75. 04/15/08 – Comments received from FDOT on traffic report and are being addressed. Working toward recommending a preferred alignment. Sarah Clarke
6064 Colonial Blvd. / Metro Pkwy. Queue Jump. 04/15/08 – Comments on 30% plans being addressed. Comments received form FDOT on the pavement design and typical section. Sarah Clarke
  Colonial initiative 04/15/08 - Selected consultant, ranking approved by BoCC 4/15/2008, will begin negotiating contract Don DeBerry
4723 Corkscrew Mitigation   Betsie Hiatt
0700 Corkscrew Road Curve. 04/15/08 –  no change, Under construction Eyra Cash
4078 CR 951 Extension. 04/15/08 - no change, Draft EIS sent to Federal Highway.  Voluntary right of way acquisition underway. Don DeBerry
4083 Cutlass Drive. 04/15/08 – no change, Preparing preliminary plans for drainage improvements and resurfacing of road, met with channel drain manufacturer to discuss product, site visit indicated that at some location the use of the valley gutter may be feasible. Rob Phelan
  Daniels Fire Station 04/15/08 - In permitting / 0.47 credits at Island Park Betsie Hiatt
TBD Daniel Parkway 4 Lane Widening. 04/15/08 – no change, Collecting available data on project Rob Phelan
6713 Daniels Pkwy. / Treeline Av. Dual Left-Turn Lane.

04/15/07 –  no change, 100% design plans complete. Received General Permit.

Eyra Cash
6713 Daniels Pkwy & Bell Tower Dr. 04/15/08 – no change, Will be bid with the Daniels and Treeline Av. project. Construction to start in 2008 Lora Celec
6713 Del Prado / Cape Coral Pkwy Turn Lane   Rob Phelan
6742 Del Prado Blvd. Median Improvements. 04/15/08 – no change, Consultant working on 100% plans. Eyra Cash
5066 Duke Highway   Randy Cerchie
5067 Estero Blvd Phase 1 03/19/08 - Held Public Meeting on March 19/08
Meet with FMB Chamber of Commerce
Meeting with BPAC April 16/08
Schedule 2 additional Public Meetings
Rob Phelan
  Estero Parkway Extension East of Ben Hill Griffin   Rob Phelan
5021 Estero Parkway from Three Oaks to Ben Hill Griffin   Nicole Maxey
0700 Evans Connector – Metro Pkwy. to Evans Ave. 04/15/08 – no change – Final report being prepared to recommend an alignment. Sarah Clarke
4043 Gator Hole Preserve Tortoise Relocation. 04/15/08 – Initial land management for Phase 2 (80 acres) complete. Initiating FWC relocation site permit. Conduct Alico / Pennslvania tortoise relocation in approximately 1 month. Betsie Hiatt
4083 Gladiolus Drive 4-Laning from Winkler to Pine Ridge Road including A&W Bulb Road and Bass Road Widening 04/15/08 – Contract approved at April 15, 2008 BOCC meeting. Updating A&W Plans based on Topo Data received from Cooner survey.
 
Rob Phelan
6002 Glenwood Ave sidewalk (Ortiz to Prospect) & Tice St (Ortiz to Lexington) 04/15/08 – no change, Under Construction. Eyra Cash
4055 Gunnery Road Under construction Nicole Maxey
6002 Gunnery Sidewalk – Lehigh HS to Buckingham Rd. 04/15/08 – no change, under construction (NTP issued 2/18/08). Sarah Clarke
5721 Hancock Bridge Extension   Sarah Clarke
4083 Hidden Lakes Mitigation Area. 04/15/08 – no change, Exotic Maintenance and monitoring ongoing. Betsie Hiatt
6713 Homestead & Milwaukee Turn Lane. 04/15/08, (Westbound left turn lane on Milwaukee Blvd.) 60% review comments are being incorporated into the design. Lora Celec
5063 Homestead Rd. – South of Sunrise to Alabama. 04/15/08 – drainage design being finalized, SFWMD permit being prepared. 60% comments have been addressed. Working toward 90% plans submittal. Sarah Clarke
6713 Homestead Rd. & Beth Stacey Blvd. 03/18/08 -Construction of roadway and signal completed. Lora Celec
6002 Homestead Rd. Sidewalk.  04/15/08 - no change, Project on hold. Sarah Clarke
4723 Imperial Marsh Preserve Wetland and Panther Mitigation Area Corkscrew Mitigation. 04/15/08 – no change Exotic Maintenance and monitoring ongoing. Betsie Hiatt
4060 Imperial Street 4-Laning from Bonita Beach Road to E. Terry Street